Building Construction If the depth of an excavation is 20 meters, number of single stage well points to be installed at various levels, is 5 4 3 6 5 4 3 6 ANSWER DOWNLOAD EXAMIANS APP
Building Construction The type of arch used for high class buildings where appearance is of prime importance, is known as Ashlar arch Axed brick arch Rubble arch Gauged brick arch Ashlar arch Axed brick arch Rubble arch Gauged brick arch ANSWER DOWNLOAD EXAMIANS APP
Building Construction The form Work including the props can be removed from beams, only after 14 days 7 days 21 days 3 days 14 days 7 days 21 days 3 days ANSWER DOWNLOAD EXAMIANS APP
Building Construction Gravels All listed here Vary in size between 2 to 20 mm Never swell when they come into contact with water Are cohesionless aggregates All listed here Vary in size between 2 to 20 mm Never swell when they come into contact with water Are cohesionless aggregates ANSWER DOWNLOAD EXAMIANS APP
Building Construction In jack arch floor, the rise is kept 1/12th of the span 1/8th of the span 1/10th of the span 1/6th of the span 1/12th of the span 1/8th of the span 1/10th of the span 1/6th of the span ANSWER DOWNLOAD EXAMIANS APP
Building Construction The maximum bearing capacity of soil is that of Hard rocks Dry coarse sandy soil Loose fine sandy soil Black cotton soil Hard rocks Dry coarse sandy soil Loose fine sandy soil Black cotton soil ANSWER DOWNLOAD EXAMIANS APP