Building Construction If the depth of an excavation is 20 meters, number of single stage well points to be installed at various levels, is 6 4 3 5 6 4 3 5 ANSWER DOWNLOAD EXAMIANS APP
Building Construction A wooden block hinged on post outside a door, is known Cleat None of these Stop Horn Cleat None of these Stop Horn ANSWER DOWNLOAD EXAMIANS APP
Building Construction Negative skin friction Develops due to lowering of ground water Is a downward drag acting on a pile due to downward movement of the surrounding compressible soil relative to the pile Neither (A) not (B) Both (A) and (B) Develops due to lowering of ground water Is a downward drag acting on a pile due to downward movement of the surrounding compressible soil relative to the pile Neither (A) not (B) Both (A) and (B) ANSWER DOWNLOAD EXAMIANS APP
Building Construction If height of the first storey of a building is 3.2 m and riser is 13 cm, the number of treads required, is 12 25 18 24 12 25 18 24 ANSWER DOWNLOAD EXAMIANS APP
Building Construction The depth of concrete bed of the foundation depends upon The upward soil pressure All listed here The mix of the concrete The projection of the concrete block beyond the footing over it The upward soil pressure All listed here The mix of the concrete The projection of the concrete block beyond the footing over it ANSWER DOWNLOAD EXAMIANS APP
Building Construction Stability of an existing structure may be disturbed by All listed here Vibrations caused by traffic movements Mining in the neighborhood Rising of water table All listed here Vibrations caused by traffic movements Mining in the neighborhood Rising of water table ANSWER DOWNLOAD EXAMIANS APP