Building Construction The raft slab is projected beyond the outer walls of the structure by 5 to 10 cm 15 to 20 cm 25 to 30 cm 30 to 45 cm 5 to 10 cm 15 to 20 cm 25 to 30 cm 30 to 45 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The form work from the underside of slabs, can be removed only after 7 days 1 day 4 days 14 days 7 days 1 day 4 days 14 days ANSWER DOWNLOAD EXAMIANS APP
Building Construction The taper of precast concrete pile should not be more than 4 cm per metre length 1 cm per metre length 5 cm per metre length 2 cm per metre length 4 cm per metre length 1 cm per metre length 5 cm per metre length 2 cm per metre length ANSWER DOWNLOAD EXAMIANS APP
Building Construction A roof which slopes in four directions, is called Gable end roof Shed roof Hipped roof Gambrel roof Gable end roof Shed roof Hipped roof Gambrel roof ANSWER DOWNLOAD EXAMIANS APP
Building Construction Cavity wall is generally provided for Sound insulation All of these Prevention of dampness Heat insulation Sound insulation All of these Prevention of dampness Heat insulation ANSWER DOWNLOAD EXAMIANS APP
Building Construction For a wall carrying heavy load on low bearing capacity soil, Lean concrete bed is provided Both (A) and (C) of the above Thick concrete bed is provided Reinforced concrete bed is provided Lean concrete bed is provided Both (A) and (C) of the above Thick concrete bed is provided Reinforced concrete bed is provided ANSWER DOWNLOAD EXAMIANS APP