Building Construction The raft slab is projected beyond the outer walls of the structure by 5 to 10 cm 15 to 20 cm 30 to 45 cm 25 to 30 cm 5 to 10 cm 15 to 20 cm 30 to 45 cm 25 to 30 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The bearing capacity of a water logged soil can be improved by Increasing the depth of foundation Draining the soil Compacting the soil Grouting Increasing the depth of foundation Draining the soil Compacting the soil Grouting ANSWER DOWNLOAD EXAMIANS APP
Building Construction The process of keeping concrete moist for a certain period after its finishing, is known as Finishing of concrete Curing of concrete Placing of concrete Compaction of concrete Finishing of concrete Curing of concrete Placing of concrete Compaction of concrete ANSWER DOWNLOAD EXAMIANS APP
Building Construction Two columns 50 cm × 50 cm and 60 cm × 60 cm carry 80 tonnes and 120 tonnes of loads respectively. The centre to centre distance between columns is 5.00 metres. The permissible bearing capacity of the soil is 20 t/m2. If the footing is not to project more than 25 cm beyond the outside of the smaller column, pick up the correct design parameters of the footing from the following: The length of the foundation slab = 7.00 m Distance of C.G. of the loads from the smaller column = 3.00 m All listed here Area of footing slab = 11.00 m2 The length of the foundation slab = 7.00 m Distance of C.G. of the loads from the smaller column = 3.00 m All listed here Area of footing slab = 11.00 m2 ANSWER DOWNLOAD EXAMIANS APP
Building Construction The maximum total settlement for raft foundation on clayey soils should be limited to 40 to 65 mm 65 to 100 mm 25 to 40 mm 25 mm 40 to 65 mm 65 to 100 mm 25 to 40 mm 25 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction Rotary drilling is the fastest method in case of All of these Sandy soil Clay soils Rocky soils All of these Sandy soil Clay soils Rocky soils ANSWER DOWNLOAD EXAMIANS APP