MGVCL Exam Paper (30-07-2021 Shift 2)
The necessary equation to be solved during the load flow analysis using Fast-Decoupled method is given below:
where B' and B'' are formed using the imaginary part of the bus admittance matrix, Ybus. If the system consists of 6 buses of which one of the bus is slack bus and 2 bues are voltage regulated buses, then then the matrix B' is of order ____and the matrix B'' is of order____, respectivity.
∆P/|Vi| = - B'∆δ
∆Q/|Vi| = - B''∆|V|

6 and 3
3 and 5
3 and 6
5 and 3

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In the context of smart meters, the term 'SMETS' stand for

Standard Metering Equipment Technical Specifications
Standard Monitoring Equipment Technical Specifications
Smart Metering Equipment Technical Specifications
Smart Monitoring Equipment Technical Specifications

ANSWER DOWNLOAD EXAMIANS APP