MGVCL Exam Paper (30-07-2021 Shift 2)
The necessary equation to be solved during the load flow analysis using Fast-Decoupled method is given below:
where B' and B'' are formed using the imaginary part of the bus admittance matrix, Ybus. If the system consists of 6 buses of which one of the bus is slack bus and 2 bues are voltage regulated buses, then then the matrix B' is of order ____and the matrix B'' is of order____, respectivity.
∆P/|Vi| = - B'∆δ
∆Q/|Vi| = - B''∆|V|

5 and 3
6 and 3
3 and 6
3 and 5

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Interposing current-transformer (CT) is used in differential protection of a transformer to

limit the main CT secondary current
increase the sensitivity of the relay
minimize the effect of saturation of the main CTs
match the standard ratio of CTs used on both sides of the transformer winding

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In a power network, 400 kV is recorded at a 415 kV bus. A 50 MVAR, 415 kV shunt reactor is connected to the bus. What is the reactive power absorbed by the shunt reactor?

46.45 MVAR
56.45 MVAR
66.45 MVAR
76.45 MVAR