The necessary equation to be solved during the load flow analysis using Fast-Decoupled method is given below:
where B' and B'' are formed using the imaginary part of the bus admittance matrix, Ybus. If the system consists of 6 buses of which one of the bus is slack bus and 2 bues are voltage regulated buses, then then the matrix B' is of order ____and the matrix B'' is of order____, respectivity.
∆P/|Vi| = - B'∆δ
∆Q/|Vi| = - B''∆|V|

3 and 6
6 and 3
5 and 3
3 and 5

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A power factor less than unity results in which of the following disadvantages?
(i) Large kVA rating of equipment
(ii)Poor voltage regulation
(iii) Greater conductor size

(i), (ii) and (iii)
(i) and (ii) only
(ii) and (iii) only
(i) and (iii) only

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
જે ક્રિયા દર્શાવે પણ વાક્યનો અર્થ પૂર્ણ કરે એ એને ____કહેવાય. - આપેલ વિકલ્પોમાંથી યોગ્યનું ચયન કરી વાક્ય પૂર્ણ કરો

કૃદંત
વિભક્તિ
ક્રિયા-વિભક્તિ
નીપાત

ANSWER DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A single phase motor connected to 415 V, 50 Hz supply takes 30 A at a power factor of 0.7 lagging. Calculate the capacitance required in parallel with the motor to raise the power factor to 0.9 lagging.

86.32 µF
66.32 µF
76.32 µF
96.32 µF

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Which one of the following statement with respect to Aerial Bunched Cables (ABC) system is TRUE?

ABC system requires more clearance, insulators and high maintenance.
The overall cost of the ABC system is very high as compared to the bare conductor system.
ABC system is not suitable for rural electrification which are situated in difficult terrain, hills, forests and coastal areas.
ABC system totally eliminates the fault on lines and thereby improving the quality of supply.

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP