MGVCL Exam Paper (30-07-2021 Shift 2)
The necessary equation to be solved during the load flow analysis using Fast-Decoupled method is given below:
where B' and B'' are formed using the imaginary part of the bus admittance matrix, Ybus. If the system consists of 6 buses of which one of the bus is slack bus and 2 bues are voltage regulated buses, then then the matrix B' is of order ____and the matrix B'' is of order____, respectivity.
∆P/|Vi| = - B'∆δ
∆Q/|Vi| = - B''∆|V|

5 and 3
3 and 5
3 and 6
6 and 3

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Which of the following is true regarding access lists applied to an interface?

One access list may be configured, per direction, for each layer 3 protocol configured on an interface
You can place as many access lists as you want on any interface until you run out of memory.
You can apply two access lists to any interface
You can apply only one access list on any interface

ANSWER DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
The miniature circuit breaker (MCB) with Class D trip characteristics trips instantaneously when the current flowing through it reaches ____ the rated current.

between 5 to 10 times
between 10 to 20 times
between 2 to 3 times
between 3 to 5 times

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Consider a solar PV plant with the following specific conditions: Analysis period: 1 year
Measured average solar irradiation intensity in 1 year: 120 kWh/m²
Generator area of the PV plant: 10 m²
Efficiency factor of the PV modules: 15%
Electrical energy actually exported by plant to grid: 110 kWh
Calculate the performance ratio.

0.5111
0.6111
0.7111
0.8111

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP