MGVCL Exam Paper (30-07-2021 Shift 2)
The necessary equation to be solved during the load flow analysis using Fast-Decoupled method is given below: where B' and B'' are formed using the imaginary part of the bus admittance matrix, Ybus. If the system consists of 6 buses of which one of the bus is slack bus and 2 bues are voltage regulated buses, then then the matrix B' is of order ____and the matrix B'' is of order____, respectivity. ∆P/|Vi| = - B'∆δ ∆Q/|Vi| = - B''∆|V|
Equivalent resistance of the circuit, Req = (12||18) + 8 Req = 7.2 + 8 Req = 15.2 ohm Source current = current through 8 ohm resistor, I = Vr/R8 I = 20/8 I = 2.5 A Supply votage V = I*Req V = 2.5*15.2 V = 38 V
The neutral point of a generator is usually earthed to facilitate protection of the stator winding and associated system. Earthing also prevents damaging transient overvoltages in the event of an arcing earth fault or ferro resonance. For HV generators, impedance is usually inserted in the stator earthing connection to limit the magnitude of earth fault current.