The necessary equation to be solved during the load flow analysis using Fast-Decoupled method is given below: where B' and B'' are formed using the imaginary part of the bus admittance matrix, Ybus. If the system consists of 6 buses of which one of the bus is slack bus and 2 bues are voltage regulated buses, then then the matrix B' is of order ____and the matrix B'' is of order____, respectivity. ∆P/|Vi| = - B'∆δ ∆Q/|Vi| = - B''∆|V|
Buchholz relay is gas operated relay. It will operate when internal fault occurs in transformer. It is placed between tank to main conservator. It has two contacts trip and alarm. Use of Buchholz relay in distribution transformer is not economical.