Power Systems The load duration curve for a system is 8 hours 30 MW, 16 hours 25 MW and 24 hours 20 MW. The load factor will be 0.83. 0.44. 0.25. 1.3. 0.83. 0.44. 0.25. 1.3. ANSWER DOWNLOAD EXAMIANS APP
Power Systems For 66 kV lines the number of insulator discs of each 11 kV used are 5 12 6 3 5 12 6 3 ANSWER DOWNLOAD EXAMIANS APP
Power Systems Surge impedance loading (SIL) is represented by both 1 and 2 Vl²*√(C/L) Vl²/Zs Vph²/Zs both 1 and 2 Vl²*√(C/L) Vl²/Zs Vph²/Zs ANSWER DOWNLOAD EXAMIANS APP
Power Systems If a generator of 250 MVA rating has an inertia constant of 6 MJ/MVA, its inertia constant on 100 MVA base is 15 MJ/MVA 6 MJ/MVA 10.5 MJ/MVA 2.5 MJ/MVA 15 MJ/MVA 6 MJ/MVA 10.5 MJ/MVA 2.5 MJ/MVA ANSWER DOWNLOAD EXAMIANS APP
Power Systems A hydro power plant of run off river type should be provided with pondage so that the pressure inside the turbine casing remains. firm capacity of plant is increased. operating head is controlled. kinetic energy of the running water is fully utilized. pressure inside the turbine casing remains. firm capacity of plant is increased. operating head is controlled. kinetic energy of the running water is fully utilized. ANSWER DOWNLOAD EXAMIANS APP
Power Systems In a thermal power plant, which of its following components needs maximum maintenance attention Steam turbine. Boiler. Super heater. Condenser. Steam turbine. Boiler. Super heater. Condenser. ANSWER DOWNLOAD EXAMIANS APP