Power Systems The load duration curve for a system is 8 hours 30 MW, 16 hours 25 MW and 24 hours 20 MW. The load factor will be 0.25. 0.44. 0.83. 1.3. 0.25. 0.44. 0.83. 1.3. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Surge impedance loading of a 3-phase, 400 kV transmission line is 400 Ω. The surge impedance loading is 1600 MW 200 MW 800 MW 400 MW 1600 MW 200 MW 800 MW 400 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems Out of the following plant categories which is not the base load power plant? Pump storage. Nuclear. Diesel. Run of river. Pump storage. Nuclear. Diesel. Run of river. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A power generating station has a plant capacity of 200 MW and maximum power demand is 150 MW. If average power generation is 110 MW, then find the load factor and capacity factor respectively? 0.65 and 0.55 0.55 and 0.733 0.733 and 0.65 0.733 and 0.55 0.65 and 0.55 0.55 and 0.733 0.733 and 0.65 0.733 and 0.55 ANSWER DOWNLOAD EXAMIANS APP
Power Systems Mercury is choice with steam in binary vapor cycle because all of above. relative low vaporization pressure. higher critical temperature and pressure. higher saturation temperature than other fluids. all of above. relative low vaporization pressure. higher critical temperature and pressure. higher saturation temperature than other fluids. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A transmission line has a surge impedance of 400 Ω is connected with the cable having surge impedance of 40 Ω, a surge magnitude of 100 kV is travelling from the transmission line towards the cable. Find the transmitted voltage? 100 kV 30.6 Kv 36. 36 kV 18.18 kV 100 kV 30.6 Kv 36. 36 kV 18.18 kV ANSWER DOWNLOAD EXAMIANS APP