Railway Engineering The height of the center of arm of a semaphore signal above the ground is 8.5m 6.5 m 7.5 m 5.5m 8.5m 6.5 m 7.5 m 5.5m ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Largest percentage of material in the rail is in its web head and foot both foot head web head and foot both foot head ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Creep is the Lateral movement of rail Difference in level of two rails Longitudinal movement of rail Vertical movement of rail Lateral movement of rail Difference in level of two rails Longitudinal movement of rail Vertical movement of rail ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Which of the following types of sleepers is preferred on joints ? steel trough sleeper CST-9 sleeper concrete sleeper wooden sleeper steel trough sleeper CST-9 sleeper concrete sleeper wooden sleeper ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering At points and crossings, the total number of sleepers for 1 in 12 turnouts in Broad Gauge is 73 72 70 71 73 72 70 71 ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The load on each axle of a locomotive is 22 tonnes. If the coefficient of friction is 0.2, then the hauling capacity due to 3 pairs of driving wheels will be 6.61 13.21 26.41 19.81 6.61 13.21 26.41 19.81 ANSWER DOWNLOAD EXAMIANS APP