Power Systems The generating station suitable to operate as peak load plant is Power station. Thermal power station. Nuclear power station. Pumped storage. Power station. Thermal power station. Nuclear power station. Pumped storage. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The area under a flow duration curve represents total power available. total of units of energy available. maximum rate of run-off during the period. total quantity of run-off during that period. total power available. total of units of energy available. maximum rate of run-off during the period. total quantity of run-off during that period. ANSWER DOWNLOAD EXAMIANS APP
Power Systems In a long transmission line, if we increase the length of the line, the parameters A and B respectively decreases and decreases increases and decreases increases and increases decreases and increases decreases and decreases increases and decreases increases and increases decreases and increases ANSWER DOWNLOAD EXAMIANS APP
Power Systems One million cubic meters of water is stored in a reservoir feeding a water turbine. The density of water is 993 kg/m³. If the centre of mass of water is 50 meters above the turbine and losses are negligible, the energy produced by that volume of water is 130.2 MWhr 135.3 MWhr 140 MWhr 120 MWhr 130.2 MWhr 135.3 MWhr 140 MWhr 120 MWhr ANSWER DOWNLOAD EXAMIANS APP
Power Systems The load current in short circuit calculations are neglected because both 1 and 2 short circuit currents are greatly out of phase with load currents short circuit currents are much larger than load currents nether 1 nor 2 both 1 and 2 short circuit currents are greatly out of phase with load currents short circuit currents are much larger than load currents nether 1 nor 2 ANSWER DOWNLOAD EXAMIANS APP
Power Systems For head and low discharge the water turbine used Pelton wheel. Francis turbine. Kaplan wheel. propeller turbine. Pelton wheel. Francis turbine. Kaplan wheel. propeller turbine. ANSWER DOWNLOAD EXAMIANS APP