Surveying The flying height of the camera is 1,000 m above mean ground level, the distance of the top of a building from a nadir point is 10 cm and the relief displacement of building is 7.2 mm. The height of the building, is 82 m 62 m 52 m 72 m 82 m 62 m 52 m 72 m ANSWER DOWNLOAD EXAMIANS APP
Surveying Triangulation surveys are carried out for locating Engineering works, i.e. terminal points of long tunnels, bridge abutments, etc. All of these Control points for surveys of large areas Control points for photogrammetric surveys Engineering works, i.e. terminal points of long tunnels, bridge abutments, etc. All of these Control points for surveys of large areas Control points for photogrammetric surveys ANSWER DOWNLOAD EXAMIANS APP
Surveying Latitude of a place is the angular distance from None of these Equator to the nearer pole Greenwich to the place Equator to the poles None of these Equator to the nearer pole Greenwich to the place Equator to the poles ANSWER DOWNLOAD EXAMIANS APP
Surveying An imaginary line lying throughout the surface of ground and preserving a constant inclination to the horizontal is known as contour interval contour line contour gradient horizontal equivalent contour interval contour line contour gradient horizontal equivalent ANSWER DOWNLOAD EXAMIANS APP
Surveying Horizontal distances obtained by thermometric observations do not require slope and tension corrections require tension correction require slope and tension corrections require slope correction do not require slope and tension corrections require tension correction require slope and tension corrections require slope correction ANSWER DOWNLOAD EXAMIANS APP
Surveying The relief displacement of a building 72 m high on photograph is 7.2 mm and its top appears 10 cm away from principal point. The flying height of the camera, is 2000 m 1500 m 1000 m 500 m 2000 m 1500 m 1000 m 500 m ANSWER DOWNLOAD EXAMIANS APP