Power Systems The flow duration curve at a given head of a hydroelectric plant is used to determine total power available at the site. diversity factor for the plant. total units of energy available. load factory at the plant. total power available at the site. diversity factor for the plant. total units of energy available. load factory at the plant. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The receiving end voltage for a long line under no load condition is more than the sending end voltage any of the above less than the sending end voltage equal to the sending end voltage more than the sending end voltage any of the above less than the sending end voltage equal to the sending end voltage ANSWER DOWNLOAD EXAMIANS APP
Power Systems Buchholz relay is used for protection of none of these. bus bar. transformer. alternator. none of these. bus bar. transformer. alternator. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The load duration curve for a system is 8 hours 30 MW, 16 hours 25 MW and 24 hours 20 MW. The load factor will be 1.3. 0.25. 0.44. 0.83. 1.3. 0.25. 0.44. 0.83. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following method is/are more reliable? Newton Raphson (NR) method Fast Decoupled Load Flow (FDLF) method All of these Gauss-Siedel (GS) method Newton Raphson (NR) method Fast Decoupled Load Flow (FDLF) method All of these Gauss-Siedel (GS) method ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following is an impulse turbine Pelton turbine. Francis turbine. None of above. Kaplan turbine. Pelton turbine. Francis turbine. None of above. Kaplan turbine. ANSWER DOWNLOAD EXAMIANS APP