Power Systems
If, for a given alternator in economic operation mode, the incremental cost is given by (0.012 P + 8) Rs/MWh, dPL/dP = 0.2 and plant λ = 25, then power generation is

 1250 MW
 750 MW
 1000 MW
 1500 MW

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The power level of nuclear reactor can be increase by ( K = multiplication factor )

 lowering the value of K below 1 but later bringing it back to K = 1.
 raising the value of K above 1 and keeping it at raised value.
  raising the value of K above 1, but later bringing it back to K = 1.
 lowering the value of K below and keeping at that lowered value.

ANSWER DOWNLOAD EXAMIANS APP