Power Systems The essential requirement(s) for power plants to be operated as peak load plants are Capability of quick starts. Low capital cost. All of these Quick response to load variation. Capability of quick starts. Low capital cost. All of these Quick response to load variation. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Find the value of a729, where "a" is the operator α 1 α² 0 α 1 α² 0 ANSWER DOWNLOAD EXAMIANS APP
Power Systems If sag in an overhead line increase, tension in the line increase remains same None of these decrease increase remains same None of these decrease ANSWER DOWNLOAD EXAMIANS APP
Power Systems If a generator of 250 MVA rating has an inertia constant of 6 MJ/MVA, its inertia constant on 100 MVA base is 6 MJ/MVA 10.5 MJ/MVA 15 MJ/MVA 2.5 MJ/MVA 6 MJ/MVA 10.5 MJ/MVA 15 MJ/MVA 2.5 MJ/MVA ANSWER DOWNLOAD EXAMIANS APP
Power Systems The inductance of single phase two wire line is given by 0.4×10-7× ln(d/r') H/m 4×10-7× ln(d/r') H/m 4×10-7× ln(r'/d) H/m 0.4×10-7× ln(r'/d) H/m 0.4×10-7× ln(d/r') H/m 4×10-7× ln(d/r') H/m 4×10-7× ln(r'/d) H/m 0.4×10-7× ln(r'/d) H/m ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following statements is/are true regarding HVDC? All of these HVDC can utilize earth for its return path There is no skin effect in dc line Corona loss is very much reduced in the dc line All of these HVDC can utilize earth for its return path There is no skin effect in dc line Corona loss is very much reduced in the dc line ANSWER DOWNLOAD EXAMIANS APP