Highway Engineering The camber for hill roads in case of bituminous surfacing is adopted as 0.03 0.02 0.04 0.025 0.03 0.02 0.04 0.025 ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering Camber in the road is provided for counteracting the centrifugal force None of these effective drainage having proper sight distance counteracting the centrifugal force None of these effective drainage having proper sight distance ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering The most suitable equipment for compacting clayey soils is a vibrator sheep foot roller pneumatic tyred roller smooth wheeled roller vibrator sheep foot roller pneumatic tyred roller smooth wheeled roller ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering The fundamental factor in the selection of pavement type is climatic condition type and intensity of traffic availability of funds for the construction project subgrade soil and drainage conditions climatic condition type and intensity of traffic availability of funds for the construction project subgrade soil and drainage conditions ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering The attainment of super elevation by rotation of pavement about the inner edge of the pavement results in balancing the earthwork does not change the vertical alignment of road avoids the drainage problem in flat terrain is preferable in steep terrain results in balancing the earthwork does not change the vertical alignment of road avoids the drainage problem in flat terrain is preferable in steep terrain ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering In highway construction on super elevated curves, the rolling shall proceed from sides towards the centre upper edge towards the lower edge lower edge towards the upper edge centre towards the sides sides towards the centre upper edge towards the lower edge lower edge towards the upper edge centre towards the sides ANSWER DOWNLOAD EXAMIANS APP