Building Construction The brick laid with its breadth parallel to the face of a wall, is known as None of these Header Closer Stretcher None of these Header Closer Stretcher ANSWER DOWNLOAD EXAMIANS APP
Building Construction The type of pointing in which upper side of mortar joints is kept about 12 mm inside the face of the masonry and bottom is kept flushed with face of wall, is Struck pointing Grooved pointing Recessed pointing Truck pointing Struck pointing Grooved pointing Recessed pointing Truck pointing ANSWER DOWNLOAD EXAMIANS APP
Building Construction The angle between skew back of a flat arch and the horizontal, is kept approximately equal to 30° 0° 90° 60° 30° 0° 90° 60° ANSWER DOWNLOAD EXAMIANS APP
Building Construction For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is 1, 2, 3, 4, 5 5, 4, 3, 2, 1 3, 2, 5, 1, 4 2, 1, 3, 5, 4 1, 2, 3, 4, 5 5, 4, 3, 2, 1 3, 2, 5, 1, 4 2, 1, 3, 5, 4 ANSWER DOWNLOAD EXAMIANS APP
Building Construction If height of the first storey of a building is 3.2 m and riser is 13 cm, the number of treads required, is 24 25 12 18 24 25 12 18 ANSWER DOWNLOAD EXAMIANS APP
Building Construction The bearing capacity of a water logged soil can be improved by Draining the soil Compacting the soil Grouting Increasing the depth of foundation Draining the soil Compacting the soil Grouting Increasing the depth of foundation ANSWER DOWNLOAD EXAMIANS APP