DGVCL Exam Paper (11-12-2011) The best location of the power factor correction equipment to be installed in the transmission line is at Middle of the line The sending end The receiving end Any place Middle of the line The sending end The receiving end Any place ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) A fuse wire should have High specific resistance and high melting point High specific resistance and low melting point Low specific resistance and high melting point Low specific resistance and low melting point High specific resistance and high melting point High specific resistance and low melting point Low specific resistance and high melting point Low specific resistance and low melting point ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) If the voltage at the two ends of a line are 132 kV, and its reactance is 40 Ω, the stability limit of the line is 435.6 MW 217.8 MW 251.5 MW 500 MW 435.6 MW 217.8 MW 251.5 MW 500 MW ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) If the excitation of a synchronous generator fails, it acts as a Induction motor Induction generator Synchronous generator Synchronous motor Induction motor Induction generator Synchronous generator Synchronous motor ANSWER EXPLANATION DOWNLOAD EXAMIANS APP if excitation of synchronous generator fails, operate as induction motor
DGVCL Exam Paper (11-12-2011) Transposition of transmission line is done to Reduce line loss Reduce corona Reduce skin effect Balance line voltage drop Reduce line loss Reduce corona Reduce skin effect Balance line voltage drop ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) Different computers are connected to a LAN by a cable and a Telephone line Special wires Interface card Modem Telephone line Special wires Interface card Modem ANSWER DOWNLOAD EXAMIANS APP