DGVCL Exam Paper (11-12-2011) The best location of the power factor correction equipment to be installed in the transmission line is at The receiving end The sending end Middle of the line Any place The receiving end The sending end Middle of the line Any place ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) An AC series circuit has R = 6 Ω, XL = 20 Ω and Xc = 12 Ω. The ciruit power factor will be 0.6 leading 0.6 lagging 0.8 lagging 0.5 leading 0.6 leading 0.6 lagging 0.8 lagging 0.5 leading ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) In a power plant, a reserve generating capacity which is not in service but is in operation is known as Hot reserve Firm power Cold reserve Spinning reserve Hot reserve Firm power Cold reserve Spinning reserve ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) If the percentage reactance of the system upto the point of fault is 20% and the base kVA is 10,000 the short ciruit kVA is 60 MVA 50 MVA 10 MVA 20 MVA 60 MVA 50 MVA 10 MVA 20 MVA ANSWER EXPLANATION DOWNLOAD EXAMIANS APP Short circuit kVA = Base kVA/%X
DGVCL Exam Paper (11-12-2011) Kilobyte, megabyte and gigabyte are measuring units used in a computer. How many megabytes make one gigabyte? 1204 1000 1042 1024 1204 1000 1042 1024 ANSWER DOWNLOAD EXAMIANS APP
DGVCL Exam Paper (11-12-2011) Which of the following power distribution system gives better reliabity ? None of these Radial system Ring main system DC 3 wire system None of these Radial system Ring main system DC 3 wire system ANSWER DOWNLOAD EXAMIANS APP