Process Equipment and Plant Design Pick out the wrong statement about routing of fluids in a shell and tube heat exchanger. Higher pressure fluid stream should be routed through the shell side The viscous fluid should be routed through the shell side The corrosive and fouling fluid should be preferably routed through the tubes Lower flow rate fluid should be routed through the shell side Higher pressure fluid stream should be routed through the shell side The viscous fluid should be routed through the shell side The corrosive and fouling fluid should be preferably routed through the tubes Lower flow rate fluid should be routed through the shell side ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The operating velocity in the absorption tower is usually 40-50% of the flooding velocity. Packed absorption towers are normally designed for a pressure drop of about __________ mm of water column per metre height of packing. 43835 20-40 1000-1500 100-150 43835 20-40 1000-1500 100-150 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design If a single tube pass heat exchanger is converted to two passes; for the same flow rate, the pressure drop per unit length in tube side will __________ times. Decrease by 22 Increase by 21.6 None of these Increase by 1.8 Decrease by 22 Increase by 21.6 None of these Increase by 1.8 ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Seamless pipe is made By extrusion & casting into static and centrifugal molds By forging a solid round, piercing it by simultaneously rotating & forcing it over a piercer point and further reducing it by rolling gas drawing Both B and C From rolled strips formed into cylinders and seam-welded By extrusion & casting into static and centrifugal molds By forging a solid round, piercing it by simultaneously rotating & forcing it over a piercer point and further reducing it by rolling gas drawing Both B and C From rolled strips formed into cylinders and seam-welded ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The distance between the top of the slots and the liquid surface when the static liquid is just ready to flow over the overflow weir is called Static submergence Skirt clearance Downcomer liquid seal None of these Static submergence Skirt clearance Downcomer liquid seal None of these ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design A stuffing box is used for Absorbing the contraction/expansion of pipeline due to temperature changes Reducing the resistance of fluid flow Facilitating smooth opening and closing of a valve Prevention of fluid leakage around moving parts Absorbing the contraction/expansion of pipeline due to temperature changes Reducing the resistance of fluid flow Facilitating smooth opening and closing of a valve Prevention of fluid leakage around moving parts ANSWER DOWNLOAD EXAMIANS APP