Building Construction Ornamental moulded course placed on the top of a wall, is Frieze Lintel Coping Cornice Frieze Lintel Coping Cornice ANSWER DOWNLOAD EXAMIANS APP
Building Construction For a wall carrying heavy load on low bearing capacity soil, Thick concrete bed is provided Both (A) and (C) of the above Reinforced concrete bed is provided Lean concrete bed is provided Thick concrete bed is provided Both (A) and (C) of the above Reinforced concrete bed is provided Lean concrete bed is provided ANSWER DOWNLOAD EXAMIANS APP
Building Construction Which one of the following activities is not correct as applicable to brick corbels Stretcher bond is generally used for the construction of brick corbel The maximum projection of the corbel should not be more than the thickness of the wall The maximum projection of each corbel course should be limited to a quarter brick at a time The discontinuous corbels are used to carry heavy concentrated loads Stretcher bond is generally used for the construction of brick corbel The maximum projection of the corbel should not be more than the thickness of the wall The maximum projection of each corbel course should be limited to a quarter brick at a time The discontinuous corbels are used to carry heavy concentrated loads ANSWER DOWNLOAD EXAMIANS APP
Building Construction Pick up the correct specification of one-room quarters generally adopted from the following: Six quarters in a row All listed here The size of room is either 3.5 m × 3 m or 4.2 m × 2.5 m The front verandah is kept 2 m wide Six quarters in a row All listed here The size of room is either 3.5 m × 3 m or 4.2 m × 2.5 m The front verandah is kept 2 m wide ANSWER DOWNLOAD EXAMIANS APP
Building Construction During percussion drilling Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole Caving or mixing of strata are caused in soft soils or cohesion-less soils All listed here The soil to a considerable depth below the bottom of the hole gets disturbed Ground water observations are hindered due to entry of the slurry in the soil below the bottom of the hole Caving or mixing of strata are caused in soft soils or cohesion-less soils All listed here The soil to a considerable depth below the bottom of the hole gets disturbed ANSWER DOWNLOAD EXAMIANS APP
Building Construction Crown is located at None of these Highest point on the extrados of the arch Skew-back of the arch Highest point on the intrados of the arch None of these Highest point on the extrados of the arch Skew-back of the arch Highest point on the intrados of the arch ANSWER DOWNLOAD EXAMIANS APP