In packed towers provided with pall rings liquid redistributors are positioned at heights of every 6 metres or 5-10 times the column diameter, whichever is less. Maximum size of the pall rings should not exceed __________ of the column diameter.

1/2 to 1/4th
1/5-1/10th
1/10-1/15th
1/20-1/30th

ANSWER DOWNLOAD EXAMIANS APP

Process Equipment and Plant Design
The centre to centre distance between two consecutive baffles in a shell and tube heat exchanger is called the baffle pitch or baffle spacing, which is more than 1/5th the I.D. of the shell. Which of the following is not a function of the baffles?

To reduce the induced vibration in the tubes
To provide support to the tube bundle
To increase the residence time of shell side fluid
To increase the tube side heat transfer co-efficient by inducing turbulence