Docks and Harbor Engineering In multiple point mooring system, vessel is secured to minimum of Eight points Two points Six points Four points Eight points Two points Six points Four points ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering By increasing the rise of lock-gates, (i) The length of the lock gate will increase (ii) Transverse stress due to water pressure on the gate will increase (iii) Compressive force on the gate will increase (i) and (ii) are correct Only (ii) is correct Only (iii) is correct (i) and (iii) are correct (i) and (ii) are correct Only (ii) is correct Only (iii) is correct (i) and (iii) are correct ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering If the maximum spring rise is 2 m and height of the waves expected is 4 m , then the breakwater height above the datum will be 4 m 5 m 2.5 m 7 m 4 m 5 m 2.5 m 7 m ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering A ship is berthed in a chamber and lifted by principles of buoyancy Such a chamber is called. Refuge dock Wet dock Dry dock Floating dock Refuge dock Wet dock Dry dock Floating dock ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering In basins subjected to strong winds and tide, the length of the berthing area should not be less than The length of design vessel + 20% clearance between adjacent vessels The length of design vessel + 10% clearance between adjacent vessels The length of design vessel Twice the length of design vessel The length of design vessel + 20% clearance between adjacent vessels The length of design vessel + 10% clearance between adjacent vessels The length of design vessel Twice the length of design vessel ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering If ‘Hs’ is the significant wave height, then the average wave height and highest wave height respectively are given by 1.27 Hs and 1.67 Hs 0.6 Hs and 1.67 Hs 1.27 Hs and 1.87 Hs 0.6 Hs and 1.87 Hs 1.27 Hs and 1.67 Hs 0.6 Hs and 1.67 Hs 1.27 Hs and 1.87 Hs 0.6 Hs and 1.87 Hs ANSWER DOWNLOAD EXAMIANS APP