Building Construction In horizontal D.P.C, thickness of cement concrete (1 : 2 : 4) is 8 cm 6 cm 2 cm 4 cm 8 cm 6 cm 2 cm 4 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction Minimum width of landing should be Half the width of stairs Equal to width of stairs One fourth the width of stairs Twice the width of stairs Half the width of stairs Equal to width of stairs One fourth the width of stairs Twice the width of stairs ANSWER DOWNLOAD EXAMIANS APP
Building Construction The window which is provided in flat roof of a room, is known Lantern window Sky window Louvered window Dormer window Lantern window Sky window Louvered window Dormer window ANSWER DOWNLOAD EXAMIANS APP
Building Construction The single stage well point system of dewatering an excavation can be used if the depth of excavation does not exceed 10 m 5 m 20 m 15 m 10 m 5 m 20 m 15 m ANSWER DOWNLOAD EXAMIANS APP
Building Construction The compaction of concrete in the drilled pile hole is done by compressed air in the case of Franki pile Vibro pile Pressure pile Simplex pile Franki pile Vibro pile Pressure pile Simplex pile ANSWER DOWNLOAD EXAMIANS APP
Building Construction For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is 5, 4, 3, 2, 1 1, 2, 3, 4, 5 2, 1, 3, 5, 4 3, 2, 5, 1, 4 5, 4, 3, 2, 1 1, 2, 3, 4, 5 2, 1, 3, 5, 4 3, 2, 5, 1, 4 ANSWER DOWNLOAD EXAMIANS APP