Building Construction In any good staircase, the maximum and minimum pitch respectively should be 40° and 25° 60° and 10° 90° and 0° 75° and 30° 40° and 25° 60° and 10° 90° and 0° 75° and 30° ANSWER DOWNLOAD EXAMIANS APP
Building Construction The depth of an arch is the distance between Crown and springing line Crown and ground level Ground level and springing line Intrados and extrados Crown and springing line Crown and ground level Ground level and springing line Intrados and extrados ANSWER DOWNLOAD EXAMIANS APP
Building Construction In horizontal D.P.C, thickness of cement concrete (1 : 2 : 4) is 8 cm 2 cm 4 cm 6 cm 8 cm 2 cm 4 cm 6 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction Which one of the following activities is not correct as applicable to brick corbels The maximum projection of each corbel course should be limited to a quarter brick at a time The discontinuous corbels are used to carry heavy concentrated loads The maximum projection of the corbel should not be more than the thickness of the wall Stretcher bond is generally used for the construction of brick corbel The maximum projection of each corbel course should be limited to a quarter brick at a time The discontinuous corbels are used to carry heavy concentrated loads The maximum projection of the corbel should not be more than the thickness of the wall Stretcher bond is generally used for the construction of brick corbel ANSWER DOWNLOAD EXAMIANS APP
Building Construction A floor constructed with 3 mm marble chips, is known Mosaic floor Chips floor Marble floor Terrazzo floor Mosaic floor Chips floor Marble floor Terrazzo floor ANSWER DOWNLOAD EXAMIANS APP
Building Construction Vertical construction joints are provided where the shearing forces are minimum in the case of All of these Beams Slabs Girders All of these Beams Slabs Girders ANSWER DOWNLOAD EXAMIANS APP