Building Construction In any good staircase, the maximum and minimum pitch respectively should be 75° and 30° 60° and 10° 40° and 25° 90° and 0° 75° and 30° 60° and 10° 40° and 25° 90° and 0° ANSWER DOWNLOAD EXAMIANS APP
Building Construction The lintels are preferred to arches because Arches require strong abutments to withstand arch thrust Arches are difficult in construction All of these Arches require more headroom to span the openings like doors, windows etc. Arches require strong abutments to withstand arch thrust Arches are difficult in construction All of these Arches require more headroom to span the openings like doors, windows etc. ANSWER DOWNLOAD EXAMIANS APP
Building Construction The construction joints in buildings are provided after 20 m 10 m 15 m 40 m 20 m 10 m 15 m 40 m ANSWER DOWNLOAD EXAMIANS APP
Building Construction The form work from the underside of slabs, can be removed only after 4 days 14 days 7 days 1 day 4 days 14 days 7 days 1 day ANSWER DOWNLOAD EXAMIANS APP
Building Construction The maximum total settlement for raft foundation on clayey soils should be limited to 40 to 65 mm 65 to 100 mm 25 to 40 mm 25 mm 40 to 65 mm 65 to 100 mm 25 to 40 mm 25 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The vertical faces of a door opening which support frame of the door, are Posts Jambs Reveals Styles Posts Jambs Reveals Styles ANSWER DOWNLOAD EXAMIANS APP