Building Construction
For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is

1, 2, 3, 4, 5
5, 4, 3, 2, 1
2, 1, 3, 5, 4
3, 2, 5, 1, 4

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Pick up the correct statements from the following:

Excessive thermal variations in the backing or plaster causes the plaster to fall
In brick work, the efflorescence is removed by applying a solution of zinc sulphate and water
Cracks appear on the plastered surface in the form of hair cracks
All listed here

ANSWER DOWNLOAD EXAMIANS APP