Building Construction Raft foundations are used for: Providing increased area of foundation over poor bearing capacity of soil Counter acting the hydrostatic effect Spanning over small soft or loose pockets All listed here Providing increased area of foundation over poor bearing capacity of soil Counter acting the hydrostatic effect Spanning over small soft or loose pockets All listed here ANSWER DOWNLOAD EXAMIANS APP
Building Construction The additional piles which are driven to increase the capacity of supporting loads on vertical piles, are known Raking piles Construction piles Sinking piles Eccentric piles Raking piles Construction piles Sinking piles Eccentric piles ANSWER DOWNLOAD EXAMIANS APP
Building Construction In ordinary residential and public buildings, the damp proof course is generally provided at Ground level Water table level Midway ground level and water-table level Plinth level Ground level Water table level Midway ground level and water-table level Plinth level ANSWER DOWNLOAD EXAMIANS APP
Building Construction Grillage foundation Is used to transfer heavy structural loads from steel columns to a soil having low bearing capacity Is light and economical All listed here Does not require deep cutting as the required base area with required pressure intensity is obtained at a shallow depth Is used to transfer heavy structural loads from steel columns to a soil having low bearing capacity Is light and economical All listed here Does not require deep cutting as the required base area with required pressure intensity is obtained at a shallow depth ANSWER DOWNLOAD EXAMIANS APP
Building Construction The type of bond in which every course contains both headers and stretchers, is called English bond Mixed bond Russian bond Flemish bond English bond Mixed bond Russian bond Flemish bond ANSWER DOWNLOAD EXAMIANS APP
Building Construction For providing a raft foundation, the following activities are involved1.Ramming the foundation bed2.Excavation of the soil upto required depth3.Laying the reinforcement over the foundation bed4.Curing the cement concrete placed over reinforcement5.Pouring the cement concrete over the reinforcementThe correct sequence is 5, 4, 3, 2, 1 2, 1, 3, 5, 4 3, 2, 5, 1, 4 1, 2, 3, 4, 5 5, 4, 3, 2, 1 2, 1, 3, 5, 4 3, 2, 5, 1, 4 1, 2, 3, 4, 5 ANSWER DOWNLOAD EXAMIANS APP