Building Construction If height of the first storey of a building is 3.2 m and riser is 13 cm, the number of treads required, is 24 25 18 12 24 25 18 12 ANSWER DOWNLOAD EXAMIANS APP
Building Construction Which of the following metal sheets is most effective in preventing dampness? Aluminium sheets Lead sheets All listed here Copper sheets Aluminium sheets Lead sheets All listed here Copper sheets ANSWER DOWNLOAD EXAMIANS APP
Building Construction The maximum total settlement for isolated foundations on clayey soils should be limited to 40 mm 100 mm 65 mm 25 mm 40 mm 100 mm 65 mm 25 mm ANSWER DOWNLOAD EXAMIANS APP
Building Construction Rotary drilling Hinders the ground water observations and permeability test Is not suitable for deposits containing very coarse gravel All listed here Is not economical for holes of less than 10 cm Hinders the ground water observations and permeability test Is not suitable for deposits containing very coarse gravel All listed here Is not economical for holes of less than 10 cm ANSWER DOWNLOAD EXAMIANS APP
Building Construction The sill of a common wooden partition is Vertical wooden member on either end Upper horizontal wooden member Intermediate horizontal wooden member Lower horizontal wooden member Vertical wooden member on either end Upper horizontal wooden member Intermediate horizontal wooden member Lower horizontal wooden member ANSWER DOWNLOAD EXAMIANS APP
Building Construction The inner section of a cavity wall, is generally known as Pillar Pilaster Buttress Leaf wall Pillar Pilaster Buttress Leaf wall ANSWER DOWNLOAD EXAMIANS APP