Waste Water Engineering Drop manholes at the junctions of sewer lines, are provided if Ordinary manhole cannot be built Sewer line runs along a main road Invert level of a branch sewer is more than 60 cm that of the main sewer Two sewer lines intersect Ordinary manhole cannot be built Sewer line runs along a main road Invert level of a branch sewer is more than 60 cm that of the main sewer Two sewer lines intersect ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Disposal to sewage in large cities, is done in Irrigation Oxidation Purification Dilution Irrigation Oxidation Purification Dilution ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The sewer which received discharge from two or more main sewers, is known as A trunk sewer An outfall sewer A main sewer An intercepting sewer A trunk sewer An outfall sewer A main sewer An intercepting sewer ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Removal of oil and grease from sewage, is known Filtration Screening None of these Skimming Filtration Screening None of these Skimming ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering Aerobic activity is maximum In sewer treatment plants In freshly produced sewage None of these At sewer pipes In sewer treatment plants In freshly produced sewage None of these At sewer pipes ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The pressure exerted by All listed here The sewage when running full from inside, is called internal pressure The internal pressure if any, causes tensile stress in the pipe material Pressure sewers are designed to be safe in tension All listed here The sewage when running full from inside, is called internal pressure The internal pressure if any, causes tensile stress in the pipe material Pressure sewers are designed to be safe in tension ANSWER DOWNLOAD EXAMIANS APP