Process Equipment and Plant Design Diameter of the seive tray column is determined by the Upper limit of the vapour velocity Hole diameter of the seive tray Lower limit of vapour velocity Height of the plate spacing Upper limit of the vapour velocity Hole diameter of the seive tray Lower limit of vapour velocity Height of the plate spacing ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design The minimum baffle height should be 3/4 of the tank height Equal to the impeller diameter Twice the tank diameter Twice the impeller diameter 3/4 of the tank height Equal to the impeller diameter Twice the tank diameter Twice the impeller diameter ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design __________ shaped roof is most commonly used for cylindrical tanks. Cone Flat Dome Umbrella Cone Flat Dome Umbrella ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design A head comprises of straight flange section, corner torus, section and central dished section. Crown radius and knuckle radius in a head is related respectively to the Corner torus section and central dished section Central dished section and corner torus section Central dished section and straight flange section Straight flange section and corner torus section Corner torus section and central dished section Central dished section and corner torus section Central dished section and straight flange section Straight flange section and corner torus section ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design A rivetted joint does not fail by __________ of rivets. Shearing Tearing of the plate across a row Tearing None of these Shearing Tearing of the plate across a row Tearing None of these ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Brass valves are usually made for pipe sizes __________ inches. >3.5 >2.5 ?1 ?2 >3.5 >2.5 ?1 ?2 ANSWER DOWNLOAD EXAMIANS APP