Process Equipment and Plant Design Corrosion allowance in the design of pressure vessel/chemical equipment is not necessary, if Wall thickness is > 30 mm Both B & C Plain carbon steel and cast iron parts are used Material of construction is high alloy steel Wall thickness is > 30 mm Both B & C Plain carbon steel and cast iron parts are used Material of construction is high alloy steel ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Wall thickness of schedule 40 pipe as compared to that of schedule 80 pipe is Less More Same Cither A or B; depends upon the I.D. of the pipe Less More Same Cither A or B; depends upon the I.D. of the pipe ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design A single pass air heater is connected to a two pass unit. For the air flow rate and other conditions remaining the same, the film heat transfer co-efficient for air will vary in the ratio of 2 20.8 20.2 None of these 2 20.8 20.2 None of these ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Shortest distance between two tubes is None of these More in case of triangular pitch as compared to square pitch of tube layout Called tube clearance Called tube pitch None of these More in case of triangular pitch as compared to square pitch of tube layout Called tube clearance Called tube pitch ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design At equal mass velocities, the values of film co-efficients for gases as compared to that for liquids are generally. Unpredictable Higher Lower Same Unpredictable Higher Lower Same ANSWER DOWNLOAD EXAMIANS APP
Process Equipment and Plant Design Tube height in a calendria type evaporator is normally less than __________ metres. 3.5 1 2 5.5 3.5 1 2 5.5 ANSWER DOWNLOAD EXAMIANS APP