Railway Engineering Consider the following statements: Automatic signalling system results in 1. greater risk 2. higher efficiency 3. avoidance of block instruments 4. higher operating cost Of these statements I and 2 are correct 3 and 4 are correct 1 and 4 are correct 2 and 3 are correct I and 2 are correct 3 and 4 are correct 1 and 4 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering For a sleeper density of (n+5), the number of sleepers required for constructing a broad gauge railway track of length 650 m is 985 975 963 900 985 975 963 900 ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering Consider the following statements about concrete sleepers. 1. They improve the track modulus. 2. They have good scrap value. 3. They render transportation easy. 4. They maintain the gauge quite satisfactorily. Of these statements 1 and 4 are correct 1 and 2 are correct 3 and 4 are correct 2 and 3 are correct 1 and 4 are correct 1 and 2 are correct 3 and 4 are correct 2 and 3 are correct ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The height of the rail for 52 kg rail section is 187 mm 162 mm 189 mm 156 mm 187 mm 162 mm 189 mm 156 mm ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering In a shunting signal if the red band is inclined at 45° it indicates stop None of these proceed proceed cautiously stop None of these proceed proceed cautiously ANSWER DOWNLOAD EXAMIANS APP
Railway Engineering The total gap on both sides between the inside edges of wheel flanges and gauge faces of the rail is kept as 16 mm 13 mm 10 mm 19 mm 16 mm 13 mm 10 mm 19 mm ANSWER DOWNLOAD EXAMIANS APP