MGVCL Exam Paper (30-07-2021 Shift 2)
Consider a solar PV plant with the following specific conditions: Analysis period: 1 year
Measured average solar irradiation intensity in 1 year: 120 kWh/m²
Generator area of the PV plant: 10 m²
Efficiency factor of the PV modules: 15%
Electrical energy actually exported by plant to grid: 110 kWh
Calculate the performance ratio.

0.8111
0.7111
0.6111
0.5111

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A single phase motor connected to 415 V, 50 Hz supply takes 30 A at a power factor of 0.7 lagging. Calculate the capacitance required in parallel with the motor to raise the power factor to 0.9 lagging.

96.32 µF
76.32 µF
86.32 µF
66.32 µF

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A three-phase, 12 kV, 50 Hz and 300 kW load is operating at 0.8 pf lag. If the pf is to be improved to unity, using star connected capacitor, the per phase value of the reactive VAR required is:

100 kVAR
25 kVAR
75 kVAR
50 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
નીચે માંથી ક્યાં રુઢિપ્રયોગનો અર્થ 'છેતરવું' એવો થાય

બે પાંદડે થવું
દસ મારવો
હથેળીમાં ચાંદ દેખાડવો
આડા ઉતરવું

ANSWER DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In a power network, 400 kV is recorded at a 415 kV bus. A 50 MVAR, 415 kV shunt reactor is connected to the bus. What is the reactive power absorbed by the shunt reactor?

76.45 MVAR
46.45 MVAR
66.45 MVAR
56.45 MVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP