MGVCL Exam Paper (30-07-2021 Shift 2)
Consider a solar PV plant with the following specific conditions: Analysis period: 1 year
Measured average solar irradiation intensity in 1 year: 120 kWh/m²
Generator area of the PV plant: 10 m²
Efficiency factor of the PV modules: 15%
Electrical energy actually exported by plant to grid: 110 kWh
Calculate the performance ratio.

0.6111
0.8111
0.7111
0.5111

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Which one of the following statement is TRUE?

Underground cables are laid at sufficient depth to avoid being unearthed easily due to removal of soil.
In the cables, sheaths are used to provide enough strength.
In the cables, the location of fault is usually found out by comparing the capacitances of insulated conductors.
The current carrying capacity of cables in DC is less than that in AC.

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP