MGVCL Exam Paper (30-07-2021 Shift 2)
Consider a solar PV plant with the following specific conditions: Analysis period: 1 year
Measured average solar irradiation intensity in 1 year: 120 kWh/m²
Generator area of the PV plant: 10 m²
Efficiency factor of the PV modules: 15%
Electrical energy actually exported by plant to grid: 110 kWh
Calculate the performance ratio.

0.5111
0.8111
0.7111
0.6111

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In a short circuit test on circuit breaker, time to reach the peak re-striking voltage is 50 µs with the peak restriking voltage of 100 kV. Determine average RRRV (Rate of rise re-striking voltage)?

3 x 10⁶ kV/sec
2 x 10⁶ kV/sec
4 x 10⁶ kV/sec
1 x 10⁶ kV/sec

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP