MGVCL Exam Paper (30-07-2021 Shift 1)
Case 1: The PV connected to the DC bus was injecting 20 kW of power constituting of 1 kW of loss
Case 2: The same PV is connected to the AC bus constituting to 1.5 kW loss. Find out the change in efficiency from Case 1 to Case 2?

2.5% increase
5% increase
5% decrease
2.5% decrease

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
In underground cables, the electrostatic stress is ___ at contactor surface and ___ at the sheath.

zero, minimum
minimum, maximum
minimum, maximum
zero, zero

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
___ is the short time reduction in the rms voltage between 0.1 to 0.9 p.u for a duration of ___

Voltage swell, 0.5 cycle to 1 minute.
Voltage sag, 0.5 cycle to 1 minute.
Voltage sag, greater than 1 minute
Voltage swell, greater than 1 minute

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
For protection of inter-turn fault in transformer, the relays preferred are

Buchholz's relay and differential relay
Overcurrent relay and Buchholz's relay
Overcurrent relay and differential relay
Buchholz's relay, overcurrent relay and differential relay

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP