MGVCL Exam Paper (30-07-2021 Shift 1)
Case 1: The PV connected to the DC bus was injecting 20 kW of power constituting of 1 kW of loss
Case 2: The same PV is connected to the AC bus constituting to 1.5 kW loss. Find out the change in efficiency from Case 1 to Case 2?

2.5% decrease
2.5% increase
5% decrease
5% increase

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
The expression for voltage regulation of a short transmission line for lagging power factor is given by: ___, where, 'I' is the line current, 'V_r' is the receiving end voltage, 'R' is the line resistance and 'X' is the line reactance.

(IX cosφ_r + IR sinφ_r)/V_r
(IR cosφ_r - IX sinφ_r)/V_r
(IR cosφ_r + IX sinφ_r)/V_r
(IX cosφ_r - IR sinφ_r)/V_r

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
The current flowing to a balanced delta connected load through line 'a' is 15 A when the conductor of line 'b' is open. With the current in line 'a' as reference, compute the symmetrical components of the line currents. Assume the phase sequence of 'abc'.

Ia₀ = 0 AIa₁ = (7.5 + j4.33) AIa₂ = (-7.5 - j4.33) A
Ia₀ = 0 AIa₁ = (7.5 - j13) AIa₂ = (7.5 + j13) A
Ia₀ = 0 AIa₁ = (-7.5 - j13) AIa₂ = (-7.5 - j4.33) A
Ia₀ = 0 AIa₁ = (7.5 + j4.33) AIa₂ = (7.5 - j 4.33) A

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
Voltage dips cannot be caused by which of the following:

Inductive Loading
Capacitive Switching
Switching on of Large Loads
Local and Remote faults

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
What is the largest thermal power plant in India?

Sasan Ultra Mega Power Plant
Vindhyachal Thermal Power Station
Mundra Thermal Power Station
Talcher Super Thermal Power Station

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP