Docks and Harbor Engineering By increasing the rise of lock-gates,(i) The length of the lock gate will increase(ii) Transverse stress due to water pressure on the gate will increase(iii) Compressive force on the gate will increase Only (ii) is correct (i) and (ii) are correct (i) and (iii) are correct Only (iii) is correct Only (ii) is correct (i) and (ii) are correct (i) and (iii) are correct Only (iii) is correct ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering Which of the following is a fixed type mooring accessory ? cables bollard anchors buoys cables bollard anchors buoys ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering Which of the following structures are constructed parallel to shore line to develop a demarcating line between land area and water area? Bulk heads, revetments and groynes Sea walls, bulk heads and groynes Sea walls, revetments and groynes Sea walls, bulk heads and revetments Bulk heads, revetments and groynes Sea walls, bulk heads and groynes Sea walls, revetments and groynes Sea walls, bulk heads and revetments ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering If H is the height of the wave expected, then the height of the breakwater is generally taken as 1.2 H to 1.25 H above the datum 1.2 H to 1.25 H above the low water level 1.2 H to 1.25 H above the high water level 1.2 H to 1.25 H above the mean sea level 1.2 H to 1.25 H above the datum 1.2 H to 1.25 H above the low water level 1.2 H to 1.25 H above the high water level 1.2 H to 1.25 H above the mean sea level ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering Minimum width of ship clearance shall be (where “B” is beam of the design vessel) B or 30 m 50 m 1.5 B 1.5 B or 50 m B or 30 m 50 m 1.5 B 1.5 B or 50 m ANSWER DOWNLOAD EXAMIANS APP
Docks and Harbor Engineering If the maximum spring rise is 2 m and height of the waves expected is 4 m , then the breakwater height above the datum will be 4 m 7 m 2.5 m 5 m 4 m 7 m 2.5 m 5 m ANSWER DOWNLOAD EXAMIANS APP