Highway Engineering Bitumen of grade 80/100 means its penetration value is 8 mm its penetration value is 8 to 10 cm its penetration value is 10 mm its penetration value is 8 to 10 mm its penetration value is 8 mm its penetration value is 8 to 10 cm its penetration value is 10 mm its penetration value is 8 to 10 mm ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering In soils having same values of plasticity index, if liquid limit is increased, then Compressibility, permeability and dry strength increase Compressibility, permeability and dry strength decrease Compressibility and permeability increase and dry strength decreases Compressibility and permeability decrease and dry strength increases Compressibility, permeability and dry strength increase Compressibility, permeability and dry strength decrease Compressibility and permeability increase and dry strength decreases Compressibility and permeability decrease and dry strength increases ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering In CBR test the value of CBR is calculated at 5.0 mm penetration only both 2.5 mm and 5.0 mm penetrations 2.5 mm penetration only 7.5 mm penetration only 5.0 mm penetration only both 2.5 mm and 5.0 mm penetrations 2.5 mm penetration only 7.5 mm penetration only ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering If the design speed is V kmph and deviation angle is N radians, then the total length of a valley curve in meters is given by the expression 3.8 NV”2 0.38 N V3/2 0.38 (NV3)”2 3.8 (NV3)”2 3.8 NV”2 0.38 N V3/2 0.38 (NV3)”2 3.8 (NV3)”2 ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering With increase in speed of the traffic stream, the maximum capacity of the lane first increases and then decreases after reaching a maximum value at optimum speed first decreases and then increases after reaching a minimum value at optimum speed decreases increases first increases and then decreases after reaching a maximum value at optimum speed first decreases and then increases after reaching a minimum value at optimum speed decreases increases ANSWER DOWNLOAD EXAMIANS APP
Highway Engineering Nagpur road plan formula were prepared by assuming rectangular or block road pattern radial or star and grid road pattern radial or star and circular road pattern radial or star and block road pattern rectangular or block road pattern radial or star and grid road pattern radial or star and circular road pattern radial or star and block road pattern ANSWER DOWNLOAD EXAMIANS APP