MGVCL Exam Paper (30-07-2021 Shift 2)
A three-phase, 12 kV, 50 Hz and 300 kW load is operating at 0.8 pf lag. If the pf is to be improved to unity, using star connected capacitor, the per phase value of the reactive VAR required is:

25 kVAR
50 kVAR
75 kVAR
100 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
The necessary equation to be solved during the load flow analysis using Fast-Decoupled method is given below:
where B' and B'' are formed using the imaginary part of the bus admittance matrix, Ybus. If the system consists of 6 buses of which one of the bus is slack bus and 2 bues are voltage regulated buses, then then the matrix B' is of order ____and the matrix B'' is of order____, respectivity.
∆P/|Vi| = - B'∆δ
∆Q/|Vi| = - B''∆|V|

3 and 6
5 and 3
3 and 5
6 and 3

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
The line currents in amperes in phases a, b and c respectively are 500 +j150, 100 – j600 and – 300 + j600 referred to the same reference vector with phase sequence of abc. Find the symmetrical component of currents.

Ia₀ = (100+j50) AIa₁ = (546.41+j165.47) AIa₂ = (-146.41-j65.47) A
Ia₀ = (100+j50) AIa₁ = (546.41+ j165.47) AIa₂ = (546.41-j165.47) A
Ia₀ = (100+j50) AIa₁ = (146.41+ j65.47) AIa₂ = (546.41-j165.47) A
Ia₀ = (100+j50) AIa₁ = (200+ j107.75) AIa₂ = (200-j107.75) A

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
A power factor less than unity results in which of the following disadvantages?
(i) Large kVA rating of equipment
(ii)Poor voltage regulation
(iii) Greater conductor size

(i) and (iii) only
(i) and (ii) only
(ii) and (iii) only
(i), (ii) and (iii)

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Replace the underlined phrase grammatically and conceptually with the help of the given options. If the given sentence is correct then select the option 'The given sentence is correct'.
The HR will give an topic to test the ability of our employees for the new project

will gives a topic to test the ability of
will give a topic to testing the ability of
will give a topic to test the ability of
The given sentence is correct

ANSWER DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
Which one of the following statement with respect to Aerial Bunched Cables (ABC) system is TRUE?

ABC system is not suitable for rural electrification which are situated in difficult terrain, hills, forests and coastal areas.
ABC system totally eliminates the fault on lines and thereby improving the quality of supply.
ABC system requires more clearance, insulators and high maintenance.
The overall cost of the ABC system is very high as compared to the bare conductor system.

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP