Power Systems
A generating station has a maximum demand of 100 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant is

 80 MW
 15 MW
 20 MW
 10 MW

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
The incremental fuel costs for two generating units G1 and G2 are given by Ic1 = 25 + 0.2 PG1 and Ic2 = 32 + 0.2 PG2, where PG1 and PG2 are real powers generated by the units. The economic allocation for a total load of 250 MW, neglecting transmission loss, is given by

 PG1 = 125 MW and PG2 = 125 MW
 PG1 = 109.75 MW and PG2 = 140.25 MW
 PG1 = 142.5 MW and PG2 = 107.5 MW
 PG1 = 100 MW and PG2 = 150 MW

ANSWER DOWNLOAD EXAMIANS APP