Power Systems A generating station has a maximum demand of 100 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant is 80 MW 15 MW 10 MW 20 MW 80 MW 15 MW 10 MW 20 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems If the fault current is 2000 A, the relay setting is 50% and CT ratio is 400 : 5, then plug setting multiplier will be 15. 50. 10. 25. 15. 50. 10. 25. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A transmission line has surge impedance of 400 Ω, operating at Vs = Vr = 400 kV line is compensated with a shunt capacitance of 30%. The line is connected to a generator delivering 200 MW. Find the load angle with out and with compensation respectively? 30° and 45° 30° and 26° 26° and 30° 45° and 26° 30° and 45° 30° and 26° 26° and 30° 45° and 26° ANSWER DOWNLOAD EXAMIANS APP
Power Systems Cheapest plant in operation and maintenance is nuclear. steam power. diesel power. hydroelectric. nuclear. steam power. diesel power. hydroelectric. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Lightning arresters are used for protection of equipment from short circuits protection of equipment from open circuits protection of equipment from external lightning All of these protection of equipment from short circuits protection of equipment from open circuits protection of equipment from external lightning All of these ANSWER DOWNLOAD EXAMIANS APP
Power Systems The rating of fuse wire is always expressed in kWh. ampere-volts. amperes. ampere-hours. kWh. ampere-volts. amperes. ampere-hours. ANSWER DOWNLOAD EXAMIANS APP