Power Systems A generating station has a maximum demand of 100 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant is 20 MW 15 MW 80 MW 10 MW 20 MW 15 MW 80 MW 10 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems Skin effect depends on conductivity relative permeability frequency All of these conductivity relative permeability frequency All of these ANSWER DOWNLOAD EXAMIANS APP
Power Systems A hydro power plant of run off river type should be provided with pondage so that the pressure inside the turbine casing remains. operating head is controlled. kinetic energy of the running water is fully utilized. firm capacity of plant is increased. pressure inside the turbine casing remains. operating head is controlled. kinetic energy of the running water is fully utilized. firm capacity of plant is increased. ANSWER DOWNLOAD EXAMIANS APP
Power Systems In hydro power stations what is an enlarged body of water just above the intake and used as a regulating reservoir called Fore bay. Penstock. Reservoir. Spillways. Fore bay. Penstock. Reservoir. Spillways. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following is/are advantages of N-R method? Time taken for each iteration is less both 1 and 2 Applicable for large power system network Number of iterations are less Time taken for each iteration is less both 1 and 2 Applicable for large power system network Number of iterations are less ANSWER DOWNLOAD EXAMIANS APP
Power Systems The corona loss on a particular system at 50 Hz is 1 kW/km per phase. What is the corona loss at 60 Hz in kW/km per phase? 1.25 0.89 1.13 1 1.25 0.89 1.13 1 ANSWER DOWNLOAD EXAMIANS APP