A power station supplies the peak load of 50 MW, 40 MW and 70 MW to three localities. The annual load factor is 0.50 p.u. and the diversity factor of the load at the station is 1.55 the maximum demand on the station and average load respectively will be

 52 MW.
 53 MW.
  51.61 MW.
 57.5 MW.