Power Systems The overall efficiency of a steam power plant equal to binary vapor cycle. the Rankine cycle. product of boiler efficiency, turbine efficiency and generator efficiency. regenerative cycle. binary vapor cycle. the Rankine cycle. product of boiler efficiency, turbine efficiency and generator efficiency. regenerative cycle. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following is/are base load plants? All of these hydro plants thermal plants nuclear plants All of these hydro plants thermal plants nuclear plants ANSWER DOWNLOAD EXAMIANS APP
Power Systems Surge impedance loading of a transmission line can be increased by addition of lumped inductance in parallel increasing its voltage level both 1 and 3 addition of lumped capacitance in series addition of lumped inductance in parallel increasing its voltage level both 1 and 3 addition of lumped capacitance in series ANSWER DOWNLOAD EXAMIANS APP
Power Systems Load frequency control is achieved by properly matching the individual machines generator ratings. reactive powers. turbine inputs. generated voltages. generator ratings. reactive powers. turbine inputs. generated voltages. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A string insulator has 4 units. The voltage across bottom most unit is 10 kV and its efficiency is 90%. Find the total operating phase voltage? 40 kV 45 kV 32 kV 36 kV 40 kV 45 kV 32 kV 36 kV ANSWER DOWNLOAD EXAMIANS APP
Power Systems The positive, negative and zero sequence per unit impedance of two generators connected in parallel are X1 = 0.12 pu, X2 = 0.096 pu and X0 = 0.036 pu. For LG fault at generator terminals (with 1 pu voltage) the positive sequence current will be 8.936 pu 7.936 pu 10.936 pu 9.936 pu 8.936 pu 7.936 pu 10.936 pu 9.936 pu ANSWER DOWNLOAD EXAMIANS APP