Power Systems The overall efficiency of a steam power plant equal to regenerative cycle. binary vapor cycle. product of boiler efficiency, turbine efficiency and generator efficiency. the Rankine cycle. regenerative cycle. binary vapor cycle. product of boiler efficiency, turbine efficiency and generator efficiency. the Rankine cycle. ANSWER DOWNLOAD EXAMIANS APP
Power Systems Binary vapor cycle are used for improving the plant efficiency. increasing the turbine efficiency. All of these improving the condenser performance. improving the plant efficiency. increasing the turbine efficiency. All of these improving the condenser performance. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A generating station has a maximum demand of 100 MW, a load factor of 60% and a plant capacity factor of 50%. The reserve capacity of the plant is 15 MW 20 MW 80 MW 10 MW 15 MW 20 MW 80 MW 10 MW ANSWER DOWNLOAD EXAMIANS APP
Power Systems A 60 Hz, 320 Km loss less line has sending end voltage 1.0 pu. The receiving end voltage on no-load is 1.088 pu. none of these. 1.116 pu. 1.1 pu. 1.088 pu. none of these. 1.116 pu. 1.1 pu. ANSWER DOWNLOAD EXAMIANS APP
Power Systems In a power system with negligible resistance, the fault current at a point is 8.00 pu. The series reactance is to be included at the fault point to limit the short circuit. current to 5.00 pu is 3.000 pu. 0.125 pu. 0.200 pu. 0.075 pu. 3.000 pu. 0.125 pu. 0.200 pu. 0.075 pu. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The time taken by the turbine to fall to 0 rpm speed from 3000 rpm is called settling time. coasting time. damping time. stopping time. settling time. coasting time. damping time. stopping time. ANSWER DOWNLOAD EXAMIANS APP