Waste Water Engineering

Waste Water Engineering
5 days-biochemical oxygen demand (BOD5) is taken at a temperature of

15°C
0°C
25°C
20°C

ANSWER DOWNLOAD EXAMIANS APP

Waste Water Engineering
¾th or ¼th extra space is left in sewer pipes at maximum discharge for

Unexpected increase in population
Large scale infiltration of storm water
All listed here
Low estimates of the average and maximum flows

ANSWER DOWNLOAD EXAMIANS APP

Waste Water Engineering
The reduced levels of the string at the consecutive sight rails A and B are 203.575 m, 203.475 m respectively. If the difference of their R.D.s is 10 m, the gradient of the sewer line is

1 in 100 upward
1 in 500 upward
1 in 100 downward
1 in 503 upward

ANSWER DOWNLOAD EXAMIANS APP

Waste Water Engineering
The grit chambers of sewage treatment plants, are generally cleaned after

12 days
2 days
14 days
7 days

ANSWER DOWNLOAD EXAMIANS APP

Waste Water Engineering
Bio-chemical oxygen demand (BOD) for the first 20 days in generally referred to

First stage demand
Initial demand
Carbonaceous demand
All of these

ANSWER DOWNLOAD EXAMIANS APP

Waste Water Engineering
If a 2% solution of sewage sample is incubated for 5 days at 20°C and the dissolved oxygen depletion was found to be 8 mg/l. The BOD of the sewage is

300 mg/l
200 mg/l
100 mg/l
400 mg/l

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Waste Water Engineering

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑