Waste Water Engineering The stone ware sewers All listed here Are manufactured from clays and shale Are used for carrying sewage and drainage from houses After casting are dried and burnt at temperature 150°C, 700°C and 1200°C All listed here Are manufactured from clays and shale Are used for carrying sewage and drainage from houses After casting are dried and burnt at temperature 150°C, 700°C and 1200°C ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The sewer pipe which carries sewage from a building for immediate disposal is Lateral sewer Main sewer House sewer Intercepting sewer Lateral sewer Main sewer House sewer Intercepting sewer ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering For sewers, inverted siphon is provided for Three pipes One pipe Four pipes Two pipes Three pipes One pipe Four pipes Two pipes ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering In detritus tanks, Organic and inorganic materials are separated All listed here Flow velocity is kept 0.09 m/sec Detention period is kept 3 to 4 minutes Organic and inorganic materials are separated All listed here Flow velocity is kept 0.09 m/sec Detention period is kept 3 to 4 minutes ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering The digested sludge from septic tanks, is removed after a maximum period of 3.5 years 4 years 3 years 5 years 3.5 years 4 years 3 years 5 years ANSWER DOWNLOAD EXAMIANS APP
Waste Water Engineering If the side of a square sewer is 1000 mm, the diameter of a hydraulically equivalent circular section, is 1065 mm 1075 mm 1045 mm 1095 mm 1065 mm 1075 mm 1045 mm 1095 mm ANSWER DOWNLOAD EXAMIANS APP