SSC JE Electrical 2019 with solution SET-2
While estimating the overhead lines, if the number of poles required is 14, then what is the estimated number of earth sets required?

2
5
3
4

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
The 2’s complement of 1010101 is

1101010
0101011
0101010
1110011

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
Four types of power plants have been given out of which three are alike in some manner and one is different. Select the odd one?

Nuclear power plant
Thermal power plant
Solar power plant
Hydro-electric power plant

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
A/An is used in domestic mixers?

Permanent magnet synchronous motor
Induction motor
Universal motor
Shaded pole motor

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP