SSC JE Electrical 2019 with solution SET-2
While estimating the overhead lines, if the number of poles required is 14, then what is the estimated number of earth sets required?

3
4
5
2

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
The number of brushes required for a 4 pole, lap wound DC machine is

8
2
4
1

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
Which of the following comes under the category of single-phase commutator motors?

Universal motor
Capacitor start motor
Shaded pole motor
Resistance start motor

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
In the two-wattmeter method of three-phase power measurement of a balanced load, if the reading of one meter is −200W, then the power factor of the load is

Greater than 0.5
Equal to 0.5
Less than 0.5
Equal to zero

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP