SSC JE Electrical 2019 with solution SET-2
While estimating the overhead lines, if the number of poles required is 14, then what is the estimated number of earth sets required?

4
3
5
2

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
While estimating domestic wiring cost, if the length of the PVC conduit required is 62 meters, then what is the length of the cable required?

62 meters
186 meters
124 meters
100 meters

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
_____type of single phase induction motor operates at better power factor at full load?

Shaded pole
Capacitor-start, induction-run
Capacitor-start, Capacitor-run
Resistance Split-phase

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP