SSC JE Electrical 2019 with solution SET-2
While estimating the overhead lines, if the number of poles required is 14, then what is the estimated number of earth sets required?

2
3
5
4

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
While estimating domestic wiring cost, if the length of the PVC conduit required is 62 meters, then what is the length of the cable required?

186 meters
62 meters
100 meters
124 meters

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
The type of insulator used on lines up to 33 kV is?
Pin insulatorReel insulator
Post insulator
Strain insulator
Choose the correct options

C, D
A, D
B, D
B, C

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
Conductors experience skin effect in

DC transmission
AC transmission
HVDC transmission
Both AC and DC transmissions

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP