SSC JE Electrical 2019 with solution SET-2
While estimating the overhead lines, if the number of poles required is 14, then what is the estimated number of earth sets required?

4
3
5
2

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
The scheduled speed of a train is______

Always greater than the average speed
Equal to average speed
Always less than the average speed
Equal to maximum speed

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
In the salient pole of the phase synchronous machine, the rotor will have

Larger diameter, larger axial length
Smaller diameter, larger axial length
Larger diameter, shorter axial length
Smaller diameter, smaller axial length

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

SSC JE Electrical 2019 with solution SET-2
The 2’s complement of 1010101 is

0101011
1101010
0101010
1110011

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP