GETCO Exam Paper (22-07-2015) Which power plant may take several days to start up and shunt down? Peak load solar power plant Base load none of these Peak load solar power plant Base load none of these ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Critical clearing time of a fault in a power system is related to Reactive power limit Transient stability limit Steady state limit Short circuit limit Reactive power limit Transient stability limit Steady state limit Short circuit limit ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In a thermal power plant, heat from the flue gases is recovered in condenser chimney Electric precipitator Economizer condenser chimney Electric precipitator Economizer ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Fuel cell for power generation have drawback of _____ Synchronization problems Very high development costs Noise, pollution and maintenance problems Low life span Synchronization problems Very high development costs Noise, pollution and maintenance problems Low life span ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) Who is the 2012 London Olympics bronze medalist in badminton? Jwala Gutta Ashwini Ponnappa Sania Saina Jwala Gutta Ashwini Ponnappa Sania Saina ANSWER DOWNLOAD EXAMIANS APP
GETCO Exam Paper (22-07-2015) In comparison to steam plant, the annual fixed cost of nuclear plant is Can't say Quit high almost equal Quit low Can't say Quit high almost equal Quit low ANSWER DOWNLOAD EXAMIANS APP