GETCO Exam Paper (22-07-2015)

GETCO Exam Paper (22-07-2015)
Which power plant may take several days to start up and shunt down?

none of these
solar power plant
Base load
Peak load

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
For a given transformer volte/turn for primary and secondary winding is

depends on load
depends on transformer design
different
same

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

emf = 4.44*f*φ*T
emf/T = 4.44*f*φ

GETCO Exam Paper (22-07-2015)
An over-current relay of current rating 5 A and setting 150% is connected to a 200/5 A CT. Then the relay to pickup, the line current required is

100
300
200
150

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
For formation of the Y bus matrix (using node voltage analysis) in power system network modelling _____ is used

KVL
KCL
all are correct
Faraday's law

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
In G-S method of power flow problem, the number of iterations _____

depends on no of buses
depends on tolerance
remains fixed
depends on voltage control buses

ANSWER DOWNLOAD EXAMIANS APP

GETCO Exam Paper (22-07-2015)
During the insulation co-ordination in the sub station, the lowest insulation strength is at

CTs and PTs
circuit breaker
transformer
bus bar

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON GETCO Exam Paper (22-07-2015)

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑