MGVCL Exam Paper (30-07-2021 Shift 2)
Which one of the following statement with respect to Aerial Bunched Cables (ABC) system is TRUE?

ABC system totally eliminates the fault on lines and thereby improving the quality of supply.
The overall cost of the ABC system is very high as compared to the bare conductor system.
ABC system requires more clearance, insulators and high maintenance.
ABC system is not suitable for rural electrification which are situated in difficult terrain, hills, forests and coastal areas.

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In a power network, 400 kV is recorded at a 415 kV bus. A 50 MVAR, 415 kV shunt reactor is connected to the bus. What is the reactive power absorbed by the shunt reactor?

56.45 MVAR
66.45 MVAR
76.45 MVAR
46.45 MVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In the context of smart meters, the term 'SMETS' stand for

Standard Monitoring Equipment Technical Specifications
Smart Metering Equipment Technical Specifications
Standard Metering Equipment Technical Specifications
Smart Monitoring Equipment Technical Specifications

ANSWER DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
જે ક્રિયા દર્શાવે પણ વાક્યનો અર્થ પૂર્ણ કરે એ એને ____કહેવાય. - આપેલ વિકલ્પોમાંથી યોગ્યનું ચયન કરી વાક્ય પૂર્ણ કરો

નીપાત
ક્રિયા-વિભક્તિ
કૃદંત
વિભક્તિ

ANSWER DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 2)
In a test by Murray loop for ground fault on 600 m of cable having a resistance of 1.5 Ω/km, the faulty cable is looped with a sound cable of the same length and area of cross section. If the ratio of the other two arms of the testing network at balance is 3 : 1, find the distance of the fault from the testing end of cables.

200 m
100 m
400 m
300 m

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP