Pick up the incorrect statement from the following. A critical ratio scheduling

All of the these
Adjusts automatically changes in activity progress
Determines the status of each activity
Establishes the relative priorities among various activities on a common basis

ANSWER DOWNLOAD EXAMIANS APP

Industrial Engineering and Production Management
The correct sequence of phases in value engineering is

Investigation phase, information phase, creative phase, evaluation phase
Creative phase, information phase, investigation phase, evaluation phase
Information phase, creative phase, investigation phase, evaluation phase
Creative phase, investigation phase, evaluation phase, information phase