Industrial Engineering and Production Management The basic difference between PERT and CPM is that Costs are considered on CPM only and not in PERT Critical path is determined in PERT only Guessed times are used in PERT and evaluated times in CPM PERT deals with events and CPM with activities Costs are considered on CPM only and not in PERT Critical path is determined in PERT only Guessed times are used in PERT and evaluated times in CPM PERT deals with events and CPM with activities ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Both Rowan plan and 50-50 Halsey plan will provide the same earning when the actual time is _________ the standard time. Equal to One-half One-fourth Twice Equal to One-half One-fourth Twice ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Dummy activities are used to Determine the project completion time Maintain the required net work Determine the critical path None of these Determine the project completion time Maintain the required net work Determine the critical path None of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The production scheduling is simpler and high volume of output and high labour efficiency are achieved in the case of Process layout A combination of line and process layout Fixed position layout Product layout Process layout A combination of line and process layout Fixed position layout Product layout ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is known as Total float Free float Duration Interfering float Total float Free float Duration Interfering float ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main disadvantage of line organisation is All of these Top level executives have to do excessive work Communication delays occur Structure is rigid All of these Top level executives have to do excessive work Communication delays occur Structure is rigid ANSWER DOWNLOAD EXAMIANS APP