Industrial Engineering and Production Management The salient feature of functional organisation is Each individual maintains functional efficiency Separation of planning and design part All of these Strict adherence to specification Each individual maintains functional efficiency Separation of planning and design part All of these Strict adherence to specification ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Frederick W. Taylor introduced a system of working known as Line organisation Functional organisation Line and staff organisation Effective organisation Line organisation Functional organisation Line and staff organisation Effective organisation ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main objective of work measurement is to Estimate the selling prices and delivery dates Formulate a proper incentive scheme All of these Plan and schedule of production Estimate the selling prices and delivery dates Formulate a proper incentive scheme All of these Plan and schedule of production ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The main disadvantage of line organisation is Communication delays occur All of these Structure is rigid Top level executives have to do excessive work Communication delays occur All of these Structure is rigid Top level executives have to do excessive work ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management CPM is the Target oriented technique Time oriented technique Event oriented technique Activity oriented technique Target oriented technique Time oriented technique Event oriented technique Activity oriented technique ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Gantt charts provide information about Determining selling price Production schedule Material handling layout Break-even point analysis Determining selling price Production schedule Material handling layout Break-even point analysis ANSWER DOWNLOAD EXAMIANS APP