Industrial Engineering and Production Management The reasons which are basically responsible for the formation of a queue should be that Output rate is constant and the input varies in a random manner All of these Output rate is linearly proportional to input The average service rate Hess than the average arrival rate Output rate is constant and the input varies in a random manner All of these Output rate is linearly proportional to input The average service rate Hess than the average arrival rate ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The time of completing a project in network analysis is given by following time of the critical activity meeting at the final triode Late finish Late start Early finish Early start Late finish Late start Early finish Early start ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Which of the following wage incentive plan guarantees minimum wage to a worker and bonus is paid for the fixed percentage of time saved? Emerson's efficiency plan Gantt plan Halsey plan Rowan plan Emerson's efficiency plan Gantt plan Halsey plan Rowan plan ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Standard time as compared to normal time is There is no such correlation Equal Greater Smaller There is no such correlation Equal Greater Smaller ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Pick up the correct step used for scheduling a project by C.P.M. Required time for each activity is established All of these A project is divided into various activities Sequence of various activities is made according to their importance Required time for each activity is established All of these A project is divided into various activities Sequence of various activities is made according to their importance ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is positive The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time The activity is critical and any delay in its performance will delay the completion of whole project Any one of the above It represents a situation where extra resources are available and the completion of project is not delayed It represents that a programme falls behind schedule and additional resources are required to complete the project in time ANSWER DOWNLOAD EXAMIANS APP