Industrial Engineering and Production Management Gantt chart is used for Inventory control Machine repair schedules Production schedule Material handling Inventory control Machine repair schedules Production schedule Material handling ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The most suitable incentive plan for the maintenance section of an industry will be Piece rate system Profit sharing plans Simplification Group incentive plan Piece rate system Profit sharing plans Simplification Group incentive plan ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management When slack of an activity is negative It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project All of these It represents that a programme falls behind schedule and additional resources are required to complete the project in time It represents a situation where extra resources are available and the completion of project is not delayed The activity is critical and any delay in its performance will delay the completion of whole project All of these ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management The most important objective behind plant layout is Economy in space Maximum travel time in plant To provide conveniently located shops Overall simplification, safety of integration Economy in space Maximum travel time in plant To provide conveniently located shops Overall simplification, safety of integration ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management Critical Path Net Work helps an engineer All of these To concentrate his attention on critical activities To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project To divert the resources from noncritical advanced activities to critical activities All of these To concentrate his attention on critical activities To be cautious for avoiding any delay in the critical activities to avoid delay of the whole project To divert the resources from noncritical advanced activities to critical activities ANSWER DOWNLOAD EXAMIANS APP
Industrial Engineering and Production Management A PERT network has three activities on critical path with mean time 3, 8 and 6 and standard deviations 1, 2 and 2 respectively. The probability that the project will be completed in 20 days is 0.5 0.84 0.66 0.95 0.5 0.84 0.66 0.95 ANSWER DOWNLOAD EXAMIANS APP