Building Construction
Which one of the following activities is not correct as applicable to brick corbels

The maximum projection of the corbel should not be more than the thickness of the wall
The maximum projection of each corbel course should be limited to a quarter brick at a time
Stretcher bond is generally used for the construction of brick corbel
The discontinuous corbels are used to carry heavy concentrated loads

ANSWER DOWNLOAD EXAMIANS APP

Building Construction
Auger boring

Is most economical up-to a depth of 5 meters
All of these
Is generally employed in cohesive and other self soils above water table
Is the most primitive method for making a hole in the ground

ANSWER DOWNLOAD EXAMIANS APP