Power Systems Which of the following statements is/are true? The elements of each row of a Y bus matrix for load flow studies in power system add up to zero always if the mutual couplings between transmission lines are absent if both 2 and 3 are satisfied if the shunt admittances at the buses are ignored always if the mutual couplings between transmission lines are absent if both 2 and 3 are satisfied if the shunt admittances at the buses are ignored ANSWER DOWNLOAD EXAMIANS APP
Power Systems When bundle conductor are used in place of single conductor the effective inductance and capacitance will respectively decrease and remain unaffected. increase and remain unaffected. increase and decrease. decrease and increase. decrease and remain unaffected. increase and remain unaffected. increase and decrease. decrease and increase. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The positive sequence reactance will be equal to negative sequence if the equipment is generator. motor. transformer and transmission lines. none of these. generator. motor. transformer and transmission lines. none of these. ANSWER DOWNLOAD EXAMIANS APP
Power Systems A generating station has a maximum demand of 50 MW a load factor of 60 %, a plant capacity factor of 45 % and if the plant while running as per schedule were fully loaded. The daily energy produced will be 710 MW. 730 MW. 740 MW. 720 MW. 710 MW. 730 MW. 740 MW. 720 MW. ANSWER DOWNLOAD EXAMIANS APP
Power Systems The positive (Z1), negative (Z2) and zero sequence (Z0) impedances of a transmission line follows the relation (Z1 = Z2) > Z0 Z1 = Z2 = Z0 any of the above (Z1 = Z2) < Z0 (Z1 = Z2) > Z0 Z1 = Z2 = Z0 any of the above (Z1 = Z2) < Z0 ANSWER DOWNLOAD EXAMIANS APP
Power Systems A power station supplies the peak load of 50 MW, 40 MW and 70 MW to three localities. The annual load factor is 0.50 p.u. and the diversity factor of the load at the station is 1.55 the maximum demand on the station and average load respectively will be 57.5 MW. 51.61 MW. 53 MW. 52 MW. 57.5 MW. 51.61 MW. 53 MW. 52 MW. ANSWER DOWNLOAD EXAMIANS APP