Highway Engineering
Which of the following methods is preferred for collecting origin and destination data for a small area like a mass business center or a large intersection ?

return postcard method
road side interview method
license plate method
home interview method

ANSWER DOWNLOAD EXAMIANS APP

Highway Engineering
For the construction of water bound macadam roads, the correct sequence of operations after spreading coarse aggregates is

dry rolling, application of screening, wet rolling and application of filler
dry rolling, application of screening, application of filler and wet rolling
dry rolling, application of filler, wet rolling and application of screening
dry rolling, wet rolling, application of screening and application of filler

ANSWER DOWNLOAD EXAMIANS APP