MGVCL Exam Paper (30-07-2021 Shift 1)
___ is the short time reduction in the rms voltage between 0.1 to 0.9 p.u for a duration of ___

Voltage sag, 0.5 cycle to 1 minute.
Voltage swell, 0.5 cycle to 1 minute.
Voltage swell, greater than 1 minute
Voltage sag, greater than 1 minute

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
A 16 A, Type B Miniature Circuit Breaker (MCB) will disconnect a fault in 0.1s when the fault current is

greater than 32 A
between 48 A and 80 A
less than 16 A
less than 16 A

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP

MGVCL Exam Paper (30-07-2021 Shift 1)
A balanced delta connected load of 8+j6 Ω per phase is connected to a 415 V, 50 Hz, 3-phase supply lines. If the input power factor is improved to 0.9 by connecting a star connected capacitor bank, then the required kVAR of the bank is

14.98 kVAR
8.98 kVAR
10.98 kVAR
16.98 kVAR

ANSWER EXPLANATION DOWNLOAD EXAMIANS APP