Power Systems Which of the following buses is/are not PV buses? voltage control buses both 1 and 2 reactive power support buses fixed shunt capacitor buses voltage control buses both 1 and 2 reactive power support buses fixed shunt capacitor buses ANSWER DOWNLOAD EXAMIANS APP
Power Systems Which of the following plants is/are base load plants both 1 and 2 run off river nuclear pump storage both 1 and 2 run off river nuclear pump storage ANSWER DOWNLOAD EXAMIANS APP
Power Systems What should be the minimum depth (in metre)of cable trench to dug for laying of 1.1 kV? 0.75. 1.20. 1.05. 0.90. 0.75. 1.20. 1.05. 0.90. ANSWER DOWNLOAD EXAMIANS APP
Power Systems a 50 Hz, 3-phase synchronous generator has inductance per phase of 15 mH. The capacitance of the generator and circuit breaker is 0.002 µF. What is its natural frequency? 29 kHz 290 kHz 29 MHz 2.9 kHz 29 kHz 290 kHz 29 MHz 2.9 kHz ANSWER DOWNLOAD EXAMIANS APP
Power Systems An over current relay, having a current setting of 125% connected to a supply circuit through a current transformer of ratio 500/5. The plug setting multiplier for a fault current of 5 kA is 5 6 2 8 5 6 2 8 ANSWER DOWNLOAD EXAMIANS APP
Power Systems Ferranti effect can be compensated by which of the following shunt reactor series capacitor shunt capacitor both 1 and 2 shunt reactor series capacitor shunt capacitor both 1 and 2 ANSWER DOWNLOAD EXAMIANS APP