Power Systems

Power Systems
If the fault current is 2000 A, the relay setting is 50% and CT ratio is 400 : 5, then plug setting multiplier will be

 50.
 15.
 10.
 25.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
A generating station has a maximum demand of 50 MW a load factor of 60 %, a plant capacity factor of 45 % and if the plant while running as per schedule were fully loaded. The daily energy produced will be

 740 MW.
 710 MW.
 730 MW.
  720 MW.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Which of the following is/are the disadvantages of phase modifiers?

 Initial cost of synchronous phase modifier is higher
 It requires more maintenance because of running equipment
All of these
 It consumes both active and reactive power

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
In case of failure of prime mover of the generator, which type of relay is used?

 distance relays
 reverse power relay
 impedance relay
 offset mho relay

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
If the time of operation of a relay for unity TMS is 10 sec. the time of operation of 0.5 TMS will be _______________ secs.

 3.
 20.
  5.
 7.

ANSWER DOWNLOAD EXAMIANS APP

Power Systems
Switchgear equipment include

  switches.
  relays and CB.
  fuses.
  all of these.

ANSWER DOWNLOAD EXAMIANS APP
MORE MCQ ON Power Systems

DOWNLOAD APP

  • APPLE
    from app store
  • ANDROID
    from play store

SEARCH

LOGIN HERE


  • GOOGLE

FIND US

  • 1.70K
    FOLLOW US
  • EXAMIANSSTUDY FOR YOUR DREAMS.
  • SUPPORT :SUPPORT EMAIL ACCOUNT : examians@yahoo.com

OTHER WEBSITES

  • GUJARATI MCQ
  • ACCOUNTIANS

QUICK LINKS

  • HOME
  • QUIZ
  • PRIVACY POLICY
  • DISCLAIMER
  • TERMS & CONDITIONS
  • CONTACT US
↑